Risk Management · 2025
In this section3 topics
Risk Management Policy & Plan
Policy & Plan Description
The Company and its group companies recognize the importance of systematic risk management under the principles of good corporate governance in order to support efficient operations and the achievement of sustainable objectives. This approach also enhances the Company’s ability to adapt to global developments and rapidly changing challenges, thereby supporting business growth opportunities. The Company has established an Enterprise Risk Management Policy by adopting the Enterprise Risk Management – Integrated Framework developed by the Committee of Sponsoring Organizations of the Treadway Commission (COSO) as the framework for risk management. In addition, the Company has defined its Risk Appetite to serve as a framework for managing organizational risks and as a guideline for business decision-making in alignment with the Company’s strategy.
The Company has also established risk management practices to serve as operational guidelines for the Company and its subsidiaries, together with internal audit activities, to ensure that operations are conducted effectively and efficiently. The Company’s risk management approach comprehensively addresses interconnected risks across all aspects, including Strategic Risk, Operational Risk, Financial Risk, Compliance Risk, Environmental, Social and Governance (ESG) Risk, Corruption Risk, and Emerging Risk, ensuring that such risks are managed within acceptable levels. In addition, the Company has established a Risk Management Committee and supporting working teams responsible for overseeing, monitoring, and supporting the successful implementation of enterprise risk management.
The Company has studied and applied various risk management tools, such as risk assessment and prioritization through the use of a Risk Map, monitoring of risk management through mitigation plans, and the use of Key Risk Indicators (KRIs). Furthermore, the Company monitors significant external factors and emerging risks through an Early Warning System (EWS) in order to enable the Company to proactively implement risk mitigation measures before such risks may affect the Company’s business operations.
Policy Document Link
https://www.gunkul.com/storage/document/cg/enterprise-risk-management-policy-en.pdf
Page Number in Report
1 - 6
Risks to the Company's Business Operations
Risk Register
| Risk Name | Risk Characteristics | Consequences | Management Measures | Related Risk Factors |
|---|---|---|---|---|
| Strategic Risk | The risk arising from reliance on government customers stems from the fact that state electricity authorities, such as the Provincial Electricity Authority, the Metropolitan Electricity Authority, and the Electricity Generating Authority of Thailand, are major customers and play a significant role in the revenue of the Company and its group companies. This is particularly relevant to the high-voltage electrical equipment business and the engineering and turnkey business related to substation construction and high-voltage transmission line projects. As a result, the Company’s operating performance is significantly linked to the policies, investment plans, and budgets of government agencies. For the high-voltage electrical equipment business, a portion of the Company’s revenue depends on government budgets allocated for power generation capacity development and electricity transmission and distribution systems. Any delay in project approvals, procurement processes, or failure to be selected through government bidding procedures may directly affect order volumes, revenue, and the Company’s operating results. With respect to the engineering and turnkey business, the associated risks are closely linked to government investment plans in electricity infrastructure. These investments aim to maintain the reliability and stability of the power system, support increasing electricity demand, and promote renewable energy development as well as national targets for reducing greenhouse gas emissions. Therefore, changes in government policies, delays in investment plans, or budget constraints in the public sector may significantly affect the Company’s business opportunities and the long-term continuity of its revenue. | Such risks may result in volatility in the Company’s revenue and operating results and may affect the volume of backlog, cash flow, profit margins, as well as the Company’s ability to expand and grow its business in the long term. | High-Voltage Electrical Equipment Business Measures to Mitigate the Impact on Current Business Operations
Measures to Enhance Alternatives and Flexibility
Engineering and Turnkey Business (related to substations and transmission lines)
| 730 · Description: Government policy · Info category: STRATEGIC_RISK · 735 · Description: Reliance on large partners / distributors or few partners / distributors · Info category: STRATEGIC_RISK · 1725 · Description: Income volatility · Info category: FINANCIAL_RISK · 737 · Other name: Business Liquidity and Public Procurement Regulations · Description: Other · Info category: STRATEGIC_RISK |
| Strategic and Regulatory Change Risks in the Public Sector | The Company’s business operations are closely associated with government energy policies and regulations, including project development, licensing for business operations, determination of power purchase tariffs, as well as various support measures or regulatory requirements related to the energy business. Such policies and regulations may be subject to change in line with government policy directions, economic conditions, and national energy trends. In addition, the Company has plans to invest in and expand into new businesses or technologies to accommodate changes in the energy industry. These developments may involve uncertainties related to regulatory frameworks, technological advancement, or market competition. Should such changes occur significantly, they may affect the Company’s strategic implementation and investment plans. | Changes in government policies or regulations may affect the conditions for business operations, project development, and the economic viability of the Company’s investments. Such changes may also require the Company to adjust its investment plans or business strategies to comply with new regulatory requirements. If the Company is unable to adapt appropriately to such changes, it may affect the Company’s investment opportunities, business growth, operating results, and long-term competitiveness. | The Company has established a dedicated team to closely monitor in-depth developments and government policies, as well as to assess potential scenarios. The results of such assessments are incorporated into the preparation of contingency business plans and financial feasibility analyses under conservative assumptions representing the lowest acceptable threshold for the Company, in order to address uncertainties related to policy changes and the business environment. In addition, during the site selection process, the Company has established procedures requiring comprehensive due diligence, including verification of land ownership and zoning regulations to confirm the feasibility of power plant construction, assessment of transmission system technical requirements, as well as compliance with bidding rules and conditions. These factors are used as criteria for selecting suitable project locations. Furthermore, the Company conducts comprehensive feasibility studies for each project across all relevant aspects, together with an assessment of all potential risks, to ensure alignment with the Company’s policies. The results of such analyses are presented to the Executive Committee, the Risk Management Committee, and the Board of Directors for careful review and risk assessment in each dimension before being submitted to the Board of Directors for investment approval. This process ensures that the Company is able to manage risks effectively, achieve its strategic investment objectives, create value for the Company, and minimize potential impacts on stakeholders within acceptable risk levels. | 756 · Description: Change in laws and regulations · Info category: COMPLIANCE_RISK · 730 · Description: Government policy · Info category: STRATEGIC_RISK · 1716 · Description: New business risk · Info category: STRATEGIC_RISK |
| Risk Related to Power Generation Capacity | The Company operates renewable energy power generation businesses, primarily solar and wind power. The nature of electricity generation from such sources relies significantly on natural resources, which may result in variability in electricity output depending on weather conditions and environmental factors. In developing each project, the Company refers to resource potential data, conducts feasibility studies, and utilizes technical modeling to estimate installed capacity, energy yield, revenue projections, and investment returns. Such analyses are carried out through a collaborative process involving the engineering team, investment analysis team, legal team, external advisors, and management personnel with extensive experience in the energy industry. Nevertheless, the electricity generation capability of each project may be affected by significant factors that may deviate from the assumptions used in project assessments. These include, among others, variability in solar irradiation or wind speeds lower than forecast levels, short-term and long-term climate change, equipment degradation occurring faster than expected, as well as equipment or control system malfunctions that may cause interruptions to electricity generation. In addition, electricity generation capacity may also be affected by other external factors, such as natural disasters (including storms, floods, or lightning strikes) and air pollution issues, including PM2.5 dust, which may prevent the Company from generating and selling electricity at the minimum levels stipulated under relevant agreements. Such circumstances may result in lower revenue, cash flow, and project returns than previously projected. | Such risks may result in electricity generation volumes falling below projected levels due to fluctuations in climatic conditions and the deterioration or reduced efficiency of generation equipment. This may directly affect revenue from electricity sales, cash flow, and the Company’s ability to comply with the conditions stipulated under the Power Purchase Agreement (PPA). In addition, such circumstances may lead to higher operating and maintenance costs, which could adversely affect the operating performance and long-term financial stability of the project. | The Company selects technologies and equipment from internationally recognized and reputable manufacturers, which are among the leading producers known for their high performance and reliability. The adoption of such technologies not only enhances electricity generation efficiency but also strengthens confidence in the long-term quality and reliability of the power plants. In addition, following the commencement of commercial operation, the Company acts as the operator responsible for the operation and maintenance of the power plants under the Operation and Maintenance Agreement (O&M Agreement). This enables the Company to effectively control and supervise the electricity generation capability as well as the operational efficiency of its solar power plants in an integrated manner, thereby mitigating risks associated with minimum electricity supply commitments under each project. Furthermore, for wind power projects, the Company has entered into maintenance agreements with turbine manufacturers to manage the operation and maintenance of the wind power plants, including spare parts management, for a period of 10 years from the date of completion of installation. A systematic maintenance plan has been implemented to ensure that the wind turbines maintain operational availability of no less than 97% on a continuous basis. In addition, prior to making investment decisions in power plant projects, the Company conducts comprehensive feasibility studies that incorporate assumptions relating to various potential risks, together with the establishment of appropriate risk management measures to mitigate potential impacts. This process ensures that investment decisions are made prudently and appropriately, and are aligned with the expected returns under an acceptable level of risk. | 741 · Description: Systems or internal control system · Info category: OPERATIONAL_RISK · 742 · Description: Human error in business operations · Info category: OPERATIONAL_RISK · 749 · Description: Safety, occupational health, and working environment · Info category: OPERATIONAL_RISK · 1719 · Description: Climate change and disasters · Info category: STRATEGIC_RISK · 1720 · Description: System disruption risk · Info category: OPERATIONAL_RISK |
| Risk of Delay in Project Commercial Operation | The Company invests in and develops various types of renewable energy power plant projects, including ground-mounted solar power projects, ground-mounted solar power projects integrated with Battery Energy Storage Systems (BESS), and wind power projects. Certain projects are currently under construction, while others remain in the development and investment planning stages. The implementation of such projects may encounter risks arising from several factors, including natural disasters, misunderstandings or concerns from local communities, contractors’ performance not meeting the project schedule, shortages of construction equipment or materials, as well as restrictions on access to construction sites. These factors may affect the progress of construction activities and may result in delays in project completion. Furthermore, the Commercial Operation Date (COD) of each project depends on several key factors, such as the completion of construction works, the receipt of licenses or approvals from relevant authorities, the availability of project financing, the execution of related agreements, as well as the results of system testing and performance verification of the power plants prior to commencement of commercial operations. Accordingly, if the Company is unable to complete project construction in accordance with the planned schedule, the commencement of commercial operations may be delayed. Such delays may affect the timing of revenue recognition for the projects and may also have an impact on the Company’s overall operating performance. | If project construction does not proceed according to the planned schedule, it may result in delays in project completion and prevent the project from achieving its Commercial Operation Date (COD) as scheduled. Such delays may cause the Company to be unable to recognize revenue from electricity sales as originally planned. In addition, project costs may increase due to higher project management expenses, financing costs, and other expenses associated with the extension of the project implementation period. Moreover, such delays may adversely affect the Company’s cash flow, operating performance, and its ability to undertake new projects in the future. It may also impact the confidence of stakeholders involved in the project. | Prior to the commencement of construction, the Company implements comprehensive preparatory measures. These include conducting studies of historical flood data covering a period of not less than 100 years and surveying site conditions before construction in order to support project design that is consistent with the geographical characteristics of the area and potential risks. At the same time, the Company promotes proper understanding among local communities and relevant stakeholders through comprehensive public consultation sessions held within the project vicinity to gather feedback and minimize potential impacts. In addition, the Company has established clear operational procedures and criteria for selecting reliable construction contractors with specialized expertise, supported by well-structured contractual arrangements to ensure effective management of construction-related risks. The Company also plans the procurement and delivery schedule of equipment to ensure alignment with the project timeline, and prepares contingency plans for equivalent substitute equipment when necessary in order to prevent delays and ensure the project can proceed continuously in accordance with the planned schedule. For projects that have already commenced construction, the Company has established risk management measures by closely monitoring construction progress. Contractors are required to provide weekly progress reports, and the Company regularly holds on-site meetings to assess the actual project status. In addition, monthly meetings are conducted with contractors to receive feedback and recommendations. Such measures enable the Company to promptly identify potential issues, obstacles, and risk factors, and to plan corrective actions or mitigation measures effectively from the early stages. For solar power projects currently under development, the Company conducts periodic monitoring of project progress and establishes contractor selection guidelines through prior consultation with financial institutions that serve as project lenders. This approach ensures that the projects meet the requirements for credit consideration and are able to secure financing in accordance with the planned timeline. Such measures support prudent management of financial and project execution risks. Furthermore, the Company enters into agreements with project developers requiring continuous support for project implementation until the Commercial Operation Date. The developer’s remuneration is structured to align with the level of project achievement, thereby creating appropriate incentives to ensure that the project progresses in accordance with the established objectives. | 739 · Description: Shortage or reliance on skilled workers · Info category: OPERATIONAL_RISK · 742 · Description: Human error in business operations · Info category: OPERATIONAL_RISK · 745 · Description: Loss or damage from non-compliance of partners or counterparties · Info category: OPERATIONAL_RISK · 1725 · Description: Income volatility · Info category: FINANCIAL_RISK · 746 · Description: Delays in the development of future projects · Info category: OPERATIONAL_RISK |
| Risk from Dependence on Engineering, Procurement and Construction (EPC) Contractors | The construction of solar power plants requires specialized expertise in technology, construction experience, the capability to procure materials, and the availability of qualified personnel to ensure that all aspects of the work are effectively coordinated. Therefore, the Company engages Engineering, Procurement and Construction (EPC) contractors to enable effective control over construction quality and project timelines, while also providing flexibility in project management to achieve the established objectives. However, such arrangements may expose the project to certain risks if the EPC contractor is unable to perform its obligations in accordance with the contract or encounters limitations in capability or financial liquidity. These circumstances may adversely affect the project schedule, project costs, and the overall success of the project. | If the main contractor delays the work or abandons the project, it may result in significant delays in project implementation. In such circumstances, the Company may be required to bear penalties for delayed delivery in accordance with the contractual terms agreed with the project owner. In addition, project costs may increase due to limited bargaining power under urgent conditions, as well as expenses related to rectification works and the engagement of replacement or backup contractors at higher-than-normal rates. These circumstances may adversely affect the operating results and overall financial position of the project. | The Company manages such risks from the contractor selection stage by engaging contractors with proven experience and expertise in the construction of solar power plants in accordance with international standards. In addition, contractual provisions are established to grant the Company the right to claim compensation for potential damages in line with industry practices and standards, thereby ensuring appropriate protection of the Company’s interests. Furthermore, the Company has established a dedicated engineering team responsible for inspecting and supervising construction quality at every stage in coordination with the contractors. The Company also conducts testing of construction works and equipment installations in accordance with engineering standards prior to formal project handover. These processes help ensure that the project meets the required quality standards and is capable of operating at optimal efficiency over the long term. | 745 · Description: Loss or damage from non-compliance of partners or counterparties · Info category: OPERATIONAL_RISK · 735 · Description: Reliance on large partners / distributors or few partners / distributors · Info category: STRATEGIC_RISK · 746 · Description: Delays in the development of future projects · Info category: OPERATIONAL_RISK |
| Human Capital Management and Workforce Capability Development Risk to Support Future Growth | The Company has experienced continuous business growth and plans to expand its investment in new projects. As a result, there is an increasing need to expand the workforce and create additional positions to support future operations. Accordingly, the Company must undertake recruitment, selection, and capability development processes to ensure that its human resources align with the Company’s growth direction. This is intended to ensure that employees possess the appropriate knowledge, competencies, and skills required to perform their duties effectively. | Such risks may affect the continuity of operations in critical positions, potentially resulting in operational gaps and reduced efficiency. This may also affect the Company’s ability to drive the organization toward achieving its established strategic objectives. In addition, employees may lack the skills and capabilities aligned with the Company’s business direction, which may limit their ability to effectively support organizational changes or future growth. This could ultimately affect the Company’s competitiveness and long-term organizational sustainability. | The Company implements a proactive recruitment process aligned with the specific needs of each business line and department, together with initiatives aimed at attracting and retaining high-potential personnel. At the same time, the Company continuously enhances employees’ knowledge and skills to ensure that its workforce remains sufficient and appropriate to support the organization’s expansion. In terms of capability development, the Company has established comprehensive personnel development plans covering multiple dimensions, including specialized knowledge, technical competencies, and skills relevant to future working environments. These include knowledge relating to artificial intelligence (AI) and related technologies in order to address potential skill gaps and strengthen employees’ readiness to support changes in business and technological developments. Furthermore, the Company regularly conducts activities to strengthen employee engagement, focusing on fostering positive relationships between employees, the organization, and their colleagues. The Company also promotes a working environment conducive to personal development and employee well-being, thereby supporting work efficiency and reducing the risk of losing high-potential personnel. For senior executives and key positions, the Company has established a structured Succession Plan. This includes systematic processes for the selection, review, monitoring, and evaluation of individual development to ensure the preparedness of potential successors, mitigate risks arising from leadership discontinuity, and support the Company’s long-term organizational growth. | 738 · Description: Reliance on employees in key positions · Info category: OPERATIONAL_RISK · 739 · Description: Shortage or reliance on skilled workers · Info category: OPERATIONAL_RISK |
| Human Rights Risk | The Company places great importance on and recognizes the need to respect internationally recognized human rights principles in order to ensure that its business operations are conducted without violations of human rights or labor rights, including freedom from discrimination in all forms. This commitment applies throughout the entire employment lifecycle, from recruitment and selection processes through the duration of employment until the termination of employment. The Company also ensures fairness and protection for individuals who may be affected by human rights violations related to the Company’s operations. The Company upholds human rights based on the principles of human dignity, justice, equality, and respect for individual freedom. It considers respect for human rights to be a key commitment and undertakes not to infringe upon the rights of all stakeholders involved in the Company’s operations, both within the organization and throughout its supply chain. In addition to safeguarding the rights of employees within the organization, the Company also emphasizes collaboration with local communities in project areas as a fundamental foundation for fostering sustainable social and community development alongside the Company’s growth. The Company also recognizes the critical importance of occupational safety, health, and strict compliance with labor laws in the construction of each project. Particular attention is given to risks related to the use of illegal labor by subcontractors, which may arise as part of the supply chain. | Any occurrence of human rights violations or unfair practices may have multidimensional impacts on the Company. These may include legal consequences arising from litigation or penalties under applicable laws, as well as reputational risks that may raise concerns among the public, investors, and other stakeholders regarding the Company’s credibility. Such incidents may also affect relationships with employees, business partners, suppliers, and local communities in project areas. In addition, they may negatively impact employee morale and work performance, as well as disrupt the continuity of project operations if opposition or distrust arises from local communities. Ultimately, these circumstances may affect the Company’s business opportunities and its long-term organizational sustainability. | The Company has established whistleblower protection measures as stipulated in its Human Rights Policy, ensuring that whistleblowers and complainants are treated fairly and protected in a safe and secure manner. In the event of any actions constituting human rights violations or breaches of the Company’s policies, the responsible parties will be subject to disciplinary actions in accordance with the Company’s regulations and may also be subject to penalties under applicable laws. This approach is intended to ensure that employees, suppliers, business partners, and all stakeholders are treated fairly, equally, and in accordance with internationally recognized human rights principles. Furthermore, the Company is committed to fostering a supportive working environment that promotes equality and sustainability under the principles of Diversity, Equity and Inclusion (DEI). All employees are entitled to equal protection and have equitable access to welfare benefits and various types of leave without discrimination based on gender identity, religion, beliefs, or personal status. For example, the Company provides leave entitlements that allow employees of all genders to take leave for gender-affirming surgery, reflecting the Company’s commitment to respecting human dignity. At the same time, the Company places importance on community participation in project areas by providing opportunities for local communities to be involved through local employment, thereby generating income and improving quality of life. The Company also conducts corporate social responsibility (CSR) activities on an ongoing basis, such as providing educational scholarships for children and youth in nearby communities. In addition, prior to the commencement of project implementation, the Company conducts public consultations to provide information on the benefits and potential impacts of the projects, while also receiving feedback from the public. Such feedback is incorporated into project management to ensure effective, transparent, and stakeholder-aligned operations. For construction activities, the Company appoints on-site safety officers responsible for regularly monitoring and supervising the performance of subcontractors. This includes ensuring compliance with occupational safety, health, and legal requirements, as well as enforcing the proper use of personal protective equipment (PPE) in accordance with established procedures to reduce the risk of workplace accidents. In addition, the Company verifies the legal employment status of workers on site to ensure compliance with labor laws. Should any cases of illegal or unfair labor practices be identified, the matter will be reported to the central management unit for immediate corrective action. These measures enable the Company to effectively manage risks related to occupational safety and illegal labor practices and ensure that operations are conducted in strict compliance with applicable laws and standards over the long term. | 749 · Description: Safety, occupational health, and working environment · Info category: OPERATIONAL_RISK · 1717 · Description: ESG risk · Info category: STRATEGIC_RISK · 753 · Description: Impact on human rights · Info category: OPERATIONAL_RISK |
| Environmental Risk | The Company recognizes environmental and climate-related risks that may arise from natural disasters and climate change, such as floods, storms, strong winds, snow, high temperatures, and dust. These factors may affect production processes, project construction, as well as the operation of power plants, particularly components such as wind turbines, solar panels, and related electrical system structures. In terms of production, flood or storm events may affect operating facilities and transportation routes for raw materials. While domestic transportation may not be significantly impacted, international transportation may be indirectly affected, potentially resulting in delays in the procurement of raw materials. Such circumstances may affect production plans and the delivery of products to customers and may also lead to additional costs or contractual penalties. With respect to project construction, severe weather conditions or natural disasters may prevent construction activities from proceeding as planned. For example, flooding in construction areas or limitations on lifting and installing equipment may cause project delays and affect the scheduled Commercial Operation Date of the project. At the same time, the Company’s operations may cause environmental impacts on surrounding areas, such as noise, traffic congestion, or dust generated from construction activities or operational processes. In addition, extreme weather conditions and airborne dust may affect electricity generation efficiency, system stability, and the long-term integrity of the Company’s assets. Accordingly, the Company places importance on systematically managing environmental risks in order to support business continuity and mitigate potential impacts on the Company’s operating performance over the long term. | Such risks may result in delays in production processes and product deliveries, affect construction schedules and the commencement of commercial operations of projects, and reduce electricity generation efficiency. In addition, these circumstances may increase operating and maintenance costs, cause damage to project assets or infrastructure, and adversely affect the Company’s revenue, cash flow, and operating results. They may also expose the Company to the risk of contractual penalties if the Company is unable to deliver works or generate electricity in accordance with contractual obligations. Furthermore, the Company’s operations—such as construction activities, equipment transportation, or the operation of power plants—may cause environmental and community impacts in surrounding areas, including noise, dust, or traffic congestion. If such impacts are not properly managed, they may lead to complaints from local communities, inspections by regulatory authorities, or risks of non-compliance with applicable environmental laws and regulations (Environmental Compliance). This may require the Company to implement additional remedial measures, incur additional costs, and potentially affect the Company’s reputation and stakeholder confidence. | The Company has established measures to carefully assess and plan the procurement of raw materials, covering the entire process from procurement to production. The Company regularly monitors the transportation status of raw materials as well as relevant information and developments that may affect supply conditions. For projects under construction, the Company plans construction activities by taking into account weather conditions and local climatic factors as key considerations in project design and operational planning. Construction schedules are arranged to align with seasonal conditions, while weather updates are closely monitored. The Company also maintains close coordination with local authorities and relevant agencies in project areas to prepare for potential emergency situations. These measures aim to ensure that construction activities can proceed efficiently and safely under appropriate environmental conditions. In addition, the Company conducts hydrological surveys and incorporates historical flood data covering the past 100 years into the design of project structures and construction layouts. This approach helps ensure that installed equipment and structures are resilient against flooding or other natural disasters that may affect the long-term stability of the projects. With respect to environmental impacts during construction, the Company operates in accordance with environmental management guidelines by controlling soil, dust, and construction materials to prevent dispersion beyond the construction site. These measures are intended to minimize disturbance to surrounding communities. At the end of each working day, the Company ensures that the construction site is properly cleaned and organized to maintain order and environmental cleanliness. For power plant projects that have already commenced commercial operations, the Company has implemented proactive risk management measures covering project design, installation, as well as the operation and maintenance of power plants in each location, tailored to the specific risk context of each area. Key measures include the following:
| 733 · Description: Business operations of partners in the supply chain · Info category: STRATEGIC_RISK · 1724 · Description: Liquidity risk · Info category: FINANCIAL_RISK · 750 · Description: Climate change and disasters · Info category: OPERATIONAL_RISK · 751 · Description: Impact on the environment · Info category: OPERATIONAL_RISK · 1717 · Description: ESG risk · Info category: STRATEGIC_RISK |
| Risk from Fluctuations in Foreign Exchange Rates and Interest Rates | The Company and its group operate businesses both domestically and internationally, including the sale of products and the procurement of goods from overseas, as well as investments in renewable energy projects abroad. As a result, the Group may be exposed to risks arising from fluctuations in foreign exchange rates. | Such risks may result in increased costs of imported goods or cause significant fluctuations in revenue and profits from overseas operations when translated into Thai Baht. This may affect the Group’s gross profit margin, operating results, and cash flow. In addition, fluctuations in foreign exchange rates and interest rates may give rise to gains or losses from the fair value measurement of financial instruments. | The Board of Directors has established a foreign exchange risk management policy, with approval authority and transaction limits specified in the Company’s Delegation of Authority Manual. The Chief Executive Officer, together with the Chief Financial Officer, is responsible for determining strategies and executing transactions related to foreign exchange risk management. In addition, operational procedures have been established for relevant personnel, and risk exposures as well as key indicators are regularly reviewed and updated. The Risk Management Committee is responsible for reviewing and monitoring the effectiveness of such risk management activities. The Group undertakes hedging transactions only for actual exposures or highly probable forecasted revenues or obligations, using appropriate financial instruments such as foreign exchange forward contracts or other suitable instruments, as deemed appropriate. | 764 · Description: Fluctuation in exchange rates, interest rates, or the inflation rate · Info category: FINANCIAL_RISK · 765 · Description: Fluctuation in return on assets or investment · Info category: FINANCIAL_RISK |
| Risk of Damage to Project Assets and Insurance Coverage | The Company and its group’s business operations may be exposed to various events that could affect business operations, including incidents that may cause damage to project assets and affect the safety of personnel during the course of their work. | Such risks may result in operational disruptions in both the short and long term, leading to reduced revenue, increased costs for repair or replacement of damaged assets, and potential impacts on project delivery schedules or electricity generation. | The Company and its group utilize insurance as one of the risk management tools to transfer certain risks from the insured to insurance providers in accordance with the terms and conditions specified in the insurance policies. In the event of damage to life or property, the insurer will provide compensation to the insured or the designated beneficiary as stipulated under the policy. All construction projects undertaken by the Group, including renewable energy projects, substations, high-voltage transmission lines, and other construction works, are covered by construction insurance policies together with third-party liability insurance and/or property insurance of the project owner to provide protection against potential damages that may occur during project implementation. In addition, upon completion of construction, the Group arranges property insurance, business interruption insurance, directors’ and officers’ liability insurance, and other relevant insurance policies, including cargo insurance for products delivered or supplied to customers. These measures are intended to mitigate the impact of potential losses that may arise at various stages of the Group’s business operations. | 746 · Description: Delays in the development of future projects · Info category: OPERATIONAL_RISK · 750 · Description: Climate change and disasters · Info category: OPERATIONAL_RISK |
| Cybersecurity and Personal Data Protection Risk | In the digital era, where information technology plays a critical role in the production and distribution of renewable energy electricity, the Company utilizes real-time Supervisory Control and Data Acquisition (SCADA) systems and Enterprise Resource Planning (ERP) systems to enhance operational efficiency. However, such technological advancements also bring increasingly sophisticated cybersecurity threats, including attempts to breach power control systems, ransomware attacks, and risks related to the leakage of confidential business information as well as personal data of customers, business partners, and employees. These incidents may affect the continuity of electricity supply, the Company’s reputation, and the confidence of stakeholders. | Such risks may result in damage to critical business information and personal data, potentially leading to financial losses, costs associated with system recovery, and the risk of legal actions under applicable laws. In addition, these incidents may adversely affect the Company’s reputation, stakeholder confidence, business continuity, and the Company’s long-term operating performance. | The Company regularly assesses cybersecurity risks and reports the results to the Risk Management Committee and the Board of Directors to ensure continuous oversight and monitoring of cyber threats. To address evolving risks, the Company places importance on regularly reviewing and maintaining fundamental cybersecurity controls, including firewall systems, intrusion detection and prevention systems (IDS/IPS), and data encryption mechanisms. Security patches for relevant software are also updated regularly to mitigate technical vulnerabilities. The Company has also implemented Two-Factor Authentication (2FA) for access to its Enterprise Resource Planning (ERP) system. Employees are required to authenticate their access through a combination of username and password together with a One-Time Password (OTP), thereby providing an additional layer of verification to prevent unauthorized access and enhance the protection of business information. In addition, the Company establishes and conducts annual testing of its IT Disaster Recovery Plan (DRP) to ensure that critical systems can be restored promptly in the event of unexpected incidents. This measure supports business continuity and reinforces confidence among stakeholders. With respect to personal data protection, the Company strictly complies with the Personal Data Protection Act B.E. 2562 (2019) (PDPA). The Company ensures proper governance throughout the entire data lifecycle, from data collection and use in accordance with the stated purposes to the secure disposal of data. The Company also provides continuous training and awareness programs for employees to foster a strong and sustainable data security culture throughout the organization. | 758 · Description: Violations of laws and regulations · Info category: COMPLIANCE_RISK · 742 · Description: Human error in business operations · Info category: OPERATIONAL_RISK · 744 · Description: Information security and cyber-attack · Info category: OPERATIONAL_RISK · 736 · Description: Damage to company image and reputation · Info category: STRATEGIC_RISK · 1720 · Description: System disruption risk · Info category: OPERATIONAL_RISK |
| Climate Change Risk | Climate change risk arises from increasing variability and severity of weather conditions, which may affect the Company’s renewable energy and construction businesses. Such risks include physical risks, such as floods, severe storms, temperature changes, earthquakes, and tsunamis, as well as uncertainties in rainfall and wind speed that may affect the efficiency of electricity generation from solar and wind energy. In addition, the Company may face strategic and financial risks arising from potential fluctuations in revenue if climatic conditions differ from the assumptions used in project investment assessments. Climate-related risks may also vary depending on the geographical context of the countries in which the Company’s projects are located. | Such risks may affect the continuity of construction activities and electricity generation operations, resulting in reduced production efficiency or damage to critical assets and infrastructure, such as solar panels, wind turbines, or power transmission systems. Such damage may lead to repair costs, revenue disruptions, and additional financial burdens. | The Company conducts climate change risk assessments across all operational areas by considering both physical risks and transition risks through a scenario analysis approach. The assessment covers short-, medium-, and long-term horizons, and the results are integrated into the Company’s Business Continuity Plan (BCP) to systematically maintain operational stability and continuity. In areas with high flood risk, the Company designs solar panel mounting structures based on historical flood data covering the past 100 years, together with the construction of embankments and drainage systems to mitigate flood risks. For wind power projects, wind speed data have been continuously collected and analyzed for more than four years in order to evaluate technical feasibility and economic viability prior to investment decisions. For operations in Japan, which are located within areas along the Ring of Fire, the Company manages such risks through risk transfer mechanisms, including insurance coverage based on assessments conducted by specialized experts to ensure that the insurance protection aligns with the potential level of damage. In addition, the Company emphasizes both climate mitigation and climate adaptation measures. The Company systematically prepares inventories and reports of organizational greenhouse gas emissions in order to establish effective emission reduction strategies and support sustainable long-term growth. | 1725 · Description: Income volatility · Info category: FINANCIAL_RISK · 746 · Description: Delays in the development of future projects · Info category: OPERATIONAL_RISK · 1719 · Description: Climate change and disasters · Info category: STRATEGIC_RISK |
Risks to Securities Holders' Investment
Risk Register
| Risk Name | Risk Characteristics | Consequences | Management Measures | Related Risk Factors |
|---|---|---|---|---|
| Risk of Investors Not Receiving the Expected Returns on Investment | The volatility of the Company’s share price, as well as sales and profit levels that may fall below shareholders’ expectations, may arise from various factors, particularly external factors beyond the Company’s control. These include domestic economic and political conditions, fluctuations in capital markets, changes in regulatory requirements governing business operations both domestically and internationally, and unforeseen crisis situations. | Such risks may result in fluctuations in the Company’s share price. | The Company is committed to managing its business operations in a sustainable and consistent manner to achieve the established objectives, with the aim of mitigating the impacts of such volatility and delivering appropriate returns to investors in line with their expectations. | 768 · Description: Return from investment of securities holder · Info category: HOLDER_RISK · 769 · Other name: Risk from Share Price Volatility · Description: Other · Info category: HOLDER_RISK |
| Risk of Investors Not Receiving Dividends as Expected | The Company intends to maintain a consistent level of dividend payments in accordance with its dividend policy, which stipulates that dividends will be paid at not less than 40 percent of the Company’s net profit as reported in the Company’s separate financial statements after deduction of corporate income tax, statutory reserves, and other reserves. However, the Company’s ability to pay dividends in certain periods may not meet investors’ expectations, as the Company may need to allocate funds for working capital requirements, business expansion investments, and other factors related to the Company’s operations and management. The Company expects that such investments will generate higher returns in the long term and enable the Company to increase dividend payments to shareholders in the future. | If the Company is unable to pay dividends in line with investors’ expectations, it may affect the confidence of shareholders and investors. | The Company has established a clear dividend policy to enhance transparency and provide predictability for investors. The Company also manages its liquidity and capital structure prudently, taking into consideration the balance between generating short-term returns through dividend payments and investing for long-term growth. In addition, the Company places importance on regularly communicating its operating results, investment plans, and business direction to shareholders in order to promote a proper understanding of the rationale for profit allocation. Such practices support the Company’s sustainable growth and are expected to strengthen its capacity to provide stable dividend payments in the future. | 768 · Description: Return from investment of securities holder · Info category: HOLDER_RISK |